Explore the report findings

The report documents recurring delivery problems in 30 selected Canadian projects. Explore what their records show about cost growth and milestone delays, and where the evidence remains limited.

Compare projects, trace proposed responses, and explore outcomes in 2D or 3D

The report reviews 30 selected projects: 26 within 1996 to 2026 and four historical comparators. These are learning cases, not a representative sample of all Canadian megaprojects.

The report's main findings, each for its own group.

Among the 8 over-budget projects in the 10 delivered projects with comparable cost records, four account for about 94% of the combined cost increase: Trans Mountain, Coastal GasLink, Muskrat Falls and Site C. This is before savings on the two projects within budget are deducted.

Among the 12 delivered projects with a documented target date, delays added up to 21.6 years. The median delay was 24% of the planned duration.

Among all 30 reviewed projects, 29 had at least one problem in the four failure patterns that usually arise at the front end, the planning and approval stage before the decision to build.

Showing all 30 selected project records.

How comparable project costs changed

Of the 22 delivered or operating projects, 10 have comparable cost records. 8 exceeded their approved budget. The report’s median growth is 20%.

The report summarizes the 10 cost records as about CAD 64 billion in approved budgets and CAD 115 billion in latest totals, an increase of about 80%.

Lower Mattagami is an interval, about -8% to 0%, not an exact final cost; it is placed last rather than given an exact rank. Each comparison retains its own budget boundary and financing treatment. Most amounts use nominal Canadian dollars (amounts reported for that year); the Pan Am baseline uses 2014 dollars. Cost labels follow the report’s whole-percentage rounding. Select a project for its figures and qualifications.

Report source: Table 4.

Read the outcome data as a table
Complete comparison groups from report Tables 4 and 5. This table retains all records when chart filters change. Comparisons marked Outside comparison are excluded, not zero.
ProjectCost growthMilestone delay
Muskrat Falls+82%38 months
Site C+82%9 months
Trans Mountain Expansion+362%53 months
Coastal GasLink+134%10 months
Keeyask Generating Station+24%28 months
Darlington Refurbishment-1%1 months
Ottawa Confederation LineOutside comparison15 months
Eglinton Crosstown LRTOutside comparison50 months
Finch West LRTOutside comparison27 months
Samuel De Champlain Bridge+6%7 months
Gordie Howe International Bridge+12%18 months
Pan Am 2015 Games+16%Outside comparison
Lower Mattagami River ProjectAbout -8% to 0%3 months

The report is not yet available to download. These views describe the selected records and the report’s proposed practices. Report announcement.